Ben Gurion International Airport, Israel

Terminal 3 – Open and Running using PULSETM

The newest terminal at Ben-Gurion International Airport. Terminal 3 has been operational for over a decade. Extending Israel’s major international airport, Terminal 3 solves passenger overload, and at the same time changes the whole area both commercially and financially. Planned as a SCADA project, Terminal 3 uses PULSETM SCADA Solution by AFCON SOFTWARE AND ELECTRONICS as the interface between most of the terminal’s systems.

PULSETM performs the following:

  • Controls/monitors/maintains 161KV high voltage power line at the Terminal 3 sub-station.
  • Controls/monitors air conditioning throughout Terminal 3 and auxiliary areas.
  • Controls 22KV high voltage power distribution.
  • Controls/monitors 25 Computerized Air Conditioning units that cool Communications rooms.
  • Treats/softens industrial water for cooling/heating processes.
  • Controls/monitors lighting system using time scheduling and timetables.
  • High voltage energy calculations and distribution after analyzing requirements at Load Shedding process.
  • Controls petrol resources and leakage from containers at fuel farm.
  • Reads/displays power levels from 300 Satec meters.
  • Controls/monitors power station built from 4 diesel generators producing up to 13.1Mw.
  • Controls water pumping and drainage systems.
  • Controls/monitors hot/cold water processing at Energy Center.
  • Controls/monitors Load Shedding process after main electricity supply shuts down.
  • Monitors Reverse Osmosis systems controlled by Omron PLCs.
  • Collects events and displays them in the PULSETM Alarm Explorer.

Architecture

  • Hot backup through PULSETM Redundancy servers (licenses for 30 stations) backed up by 2 Ethernet ports from 2 different multi-line switches. Between servers an Ethernet connection is the replication line for data synchronization.
  • Thirty workstations attached to multi-lined Ethernet through link protectors. During failure systems automatically move to secondary switch, which works without interruption.
  • Three pairs of Quantum drivers in hot standby network managing all systems electricity and electro-mechanics from the power station and secondary high voltage power station.
  • Application is divided into five sub-projects enabling dynamic jumps between workstations.
  • Two workstations in Engineers' room where SNMP networking project was developed and is monitored.
  • All links to master PLCs are through optic fiber network cells between Main Power Station to master PLC communications cupboard.
  • On Alarms/Events server workstation the Alarm Explorer displays system-wide events/alarms.
  • Each RTU has master PLC drivers that compare instructions for running/collecting information from the PULSETM interface and the connection, enabling efficient transfer of many values.


Systems and Links to PULSETM

  • Eight medium voltage chillers, each producing 200 tons of cooled air and controlled by an independent PLC. Data collection/transfer is through a YORKTALK controller.
    Three heated water tanks controlling humidity temperature. Tank values are read through communication from PULSETM to the tank’s CB HAWK PLC.
  • Water treatment/softener systems values read by GE PLC and displayed on PULSETM interface.
  • Values are read from the Diesel Generation Power Station by 4 Modicon Premium PLCs.
  • PULSETM remotely controls/monitors 21 main links using CSI drivers for temperature control throughout. Each station has many drivers, totaling over 300 CSI drivers and 18,000 I/Os.
  • PULSETM remotely controls/monitors 31 master PLCs collecting values from PULSETM  to areas with up to 10 Remote Terminal Units (RTUs) for each master PLC.
  • Each RTU manages a module of I/O numbers totaling 20,000 I/Os.
  • Each RTU controls low/high voltage circuit breaker systems, such as; elevators, UPS, passenger loading bridges, escalators, and speed walks.

Members Log-in

Some information is accessible to members only. To access please login or register.
Remember Me
Registration
Forgot your password?
Submit
Username and/or password are incorrect. Please try again.

An Email with your Username and Password was sent to you

Please get your details from the Email and try again

Please check your UserName and try again
Please enter your Email and press "Go" to start the password recovery process